Collaboration Efficiency: Analyzing Bricklayer Completion Time

Collaboration Efficiency: Analyzing Bricklayer Completion Time

Introduction

Collaboration among workers is a common practice in construction and various other industries. This article delves into a practical problem and its resolution, focusing on the individual and combined work rates of two bricklayers to determine the total time taken to complete a wall.

Problem Statement and Initial Determination of Work Rates

The first bricklayer can build a wall in 3 days, while the second bricklayer takes 4 days to complete the same task. The first bricklayer starts working alone but later joins the second bricklayer to finish the wall. The challenge is to determine the total time it takes to build the wall considering both scenarios.

Calculating Individual Work Rates

Let's begin by calculating the individual work rates of the bricklayers.

First Bricklayer's Work Rate: Since the first bricklayer can build the wall in 3 days, his work rate is: Rate of first bricklayer 1 wall / 3 days 1/3 walls per day Second Bricklayer's Work Rate: The second bricklayer can build the wall in 4 days, so his work rate is: Rate of second bricklayer 1 wall / 4 days 1/4 walls per day

Work Done by the First Bricklayer in One Day

In one day, the first bricklayer can complete:

Work done by first bricklayer in 1 day 1/3 walls

Determining the Remaining Work

After the first bricklayer works alone for one day, the amount of work left to do is:

Remaining work 1 - 1/3 2/3 walls

Combined Work Rate of Both Bricklayers

The combined work rate of both bricklayers is:

Combined rate 1/3 1/4 4/12 3/12 7/12 walls per day

Time to Finish the Remaining Work Together

Let t be the time in days it takes for both bricklayers to finish the remaining 2/3 of the wall:

7/12 t 2/3

Multiplying both sides by 12 to clear the fraction:

7t 8

Dividing both sides by 7:

t 8/7 days

Total Time to Build the Wall

The total time taken to build the wall is the 1 day the first bricklayer worked alone plus the time they worked together:

Total time 1 8/7 15/7 days

Converting this to a mixed number:

15/7 2 1/7 days

Approximately, this is 2 days and about 3 hours.

Alternative Method for Verification

Using the alternative method where the total work is considered as 12 units:

Work done by first bricklayer in a day: 12/3 4 units Work done by second bricklayer in a day: 12/4 3 units Work done by both bricklayers in a day when working together: 4 3 7 units Total work to complete: 12 units Time taken together to complete the remaining work: 7x 8 x 8/7 days

Approximately 1 day and 3 hours.

Conclusion

The total time taken to build the wall, considering both methods, is effectively the solution to the problem. This example demonstrates the importance of understanding individual and combined work rates in problem-solving, which is crucial in construction and project management.